Control Room Operator

Competency-based
ONET: 51-8012.00

2

Years

70

Skills

235h

Related instructions
Curriculum
  • Performing Start-Up, Trip Recovery, Plant Controls and Signal Diagrams
  • Performing Normal Operations on Start-Up, Shut-Down, and Trip Recovery
  • Performing Trip Recovery and Malfunctions Response
  • Responding to Major Malfunctions and Performing Start-Up and Recovery
  • Supporting Apprentices Through On-The-Job Training
  • Final Exam and Review
  • Performing Start-Up, Trip Recovery, Plant Controls & Signal Diagrams Simulator Time
On-the-job training
  • Performing Startup, Trip Recovery, Plant Controls and Signal Diagrams
    • Lock open the boiler feed pump recirculation valves
    • Operate the Unit 3 steam face coils to put in service and lock down
    • Operate the drum level control manually
    • Admit seal steam to G-Heater
    • Start the submerged flight conveyor on Unit 3
    • Start the economizer on lower dry flight on Unit 3
    • Start the economizer on upper dry flight on Unit 3
    • Start the SCR on lower dry flight on Unit 2
    • Start the SCR on upper dry flight on Unit 2
    • Start up at farm on the ammonia system on Unit 2
    • Start the start-up boiler feed pump
    • Start a main condenser hotwell pump with no pumps running
    • Start a main condenser hotwell pump with one pump running
    • Start a second boiler feed pump turbine
    • Adjust air flow to influence re-heat temperature
    • Start an air heater
    • Start an induced draft fan
    • Start a forced draft fan
    • Purge the boiler
    • Start a primary air fan
    • Start an electrical hydraulic control pump
    • Calculate maximum allowable top to bottom drum metal temperature differential
    • Blow soot in the boiler
    • Establish turbine rotor pre-warm
    • Activate the wobulator
    • Apply steam seals to the turbine and pull vacuum on the main condenser
  • Performing Normal Operations on Start-Up, Shut-Down, and Trip Recovery
    • Establish light off air flow on a individual mill package
    • Increase the bias on B pulverizer group
    • Start a set of gas lighters
    • Automate an pulverizer mill package
    • Fill the cooling tower basin
    • Fill the circulating water tunnels
    • Start a cooling tower fan
    • Start a circulating water pump
    • Automate the boiler master
    • Automate the fuel master
    • Place the stator cooling water system in service
    • Test the main control valves
  • Performing Trip Recovery and Malfunctions Response
    • Perform an emergency stop on a pulverizer mill package
    • Demonstrate the response to high pulverizer mill differential pressure
    • Demonstrate the response to a coal feeder trip
    • Demonstrate the response to a pulverizer fire
    • Automate the super heat spray controls
    • Automate the reheat spray controls
    • Place the turbine on turning gear
    • Calculate the correct acceleration rate for the turbine using the turbine starting and loading instructions
    • Synchronize the generator and close the main generator breaker
    • Calculate maximum allowable VAR load for a given megawatt load using the generator capability curve
    • Increase generator terminal voltage
    • Operate the unit in boiler follow mode
    • Operate the unit in turbine follow mode
    • Operate the unit in megawatt control with boiler follow mode
  • Responding to Major Malfunctions and Performing Start-Up and Recovery
    • Bypass feed water flow around a high pressure heater (Simulator)
    • Demonstrate the response to a deaerator high level trip (Simulator)
    • Demonstrate the respond to a boiler feed pump turbine trip (Simulator)
    • Demonstrate the response to a forced draft fan trip (Simulator)
    • Demonstrate the response to an induced draft fan trip (Simulator)
    • Demonstrate the response to a circulation pump trip (Simulator)
    • Demonstrate the response to a scrubber booster fan trip (Simulator)
    • Properly operate the turbine with A heater out of service
    • Demonstrate the proper response to a turbine trip
    • Demonstrate the proper response to a boiler trip
    • Establish normal back-feed for the in-house electrical distribution system
    • Perform deicing on a cooling tower
  • Maintaining Safe Work Practices with Breakers and Arc Flash
    • Maintain safe work practices
    • Identify the OSHA requirements to protect against electrical and arc hazards
    • Identify low voltage circuit breakers, circuit breakers and motors
  • Supporting Apprentices through On-the-job training
    • Identify DOL regulations and Labor Agreement for journeymen working with apprentices
    • Conduct pre-job briefing
    • Communicate effectively with apprentices
Interested in this apprenticeship?
Sign up to receive notifications about changes and updates about Control Room Operator
Headquarters location
Farmville, NC (27828)
Get on our calendar
Not sure if WorkHands is right for you? Chat with our team today
Send us an email
We'll get back to you shortly